Summer 2025 Construction Alert

From May 12th - August 8th, ºÚÁÏÃÅwill undergo several construction projects to improve the campus facilities. Please take note of the following projects: 

  • 6347 N. Broadway Renovations
  • Campion Hall Demolition
  • Campus IT Infrastructure Updates
  • Cudahy Library Exterior Renovations
  • Cudahy Science Exterior Renovations
  • Golf and Softball Practice Facilities and Mertz Amenity Deck Renovations
  • Granada Center Storefront Signage
  • Ignatius House Roof Renovations
  • Madonna della Strada Exterior Renovations
  • St. Louis Hall Exterior Renovations

These projects are necessary to ensure the long-term sustainability and improvement of our campus. Thank you for your understanding during this time. If you have any questions or concerns, please do not hesitate to reach out to us. 

Please click on the link below for the logistics plan and additional project detail.

Summer Construction 2025

 

Elevator Modernization Program

PROJECT INFORMATION:

As part of Loyola’s ongoing maintenance and replacement schedule, the elevator modernization project will be addressing aging systems requiring upgrades to provide improved controls, reliability, and efficiency. This program will address elevators across several campuses.

Buildings that are part of this program as well as the anticipated schedule per car:

BUILDING ELEVATOR MODERNIZATION PROJECT STATUS
LAKE SHORE CAMPUS  
BVM Hall Passenger Car #1 completed Summer 2024
  Passenger Car #2 completed November 2024
Mertz Hall Freight Car Summer 2025
Mundelein Center Passenger Car #3 completed Summer 2024
  Passenger Car #5 completed September 2024
  Passenger Car #6 completed January 2025
  Passenger Car #4 May 2025 – August 2025
  Passenger Car #2 March 2025 – May 2025
  Passenger Car #1 May 2025 – August 2025
HEALTH SCIENCES CAMPUS  
Cuneo Center Passenger Car #1 completed October 2024
  Passenger Car #2 completed December 2024
  Freight Car #3 December 2024- April 2025
WATER TOWER CAMPUS  
Baumhart Hall Passenger Car 2024 - 3 completed March 2025; 4th to be complete Summer 2025
Lewis Towers* Passenger Car #2 completed December 2024
  Passenger Car #3 December 2024 - May 2025
  Passenger Car #1 January 2025 - April 2025
  Passenger Car #4 May 2025 - July 2025
  Freight Car #5 April 2025 - June 2025
  Freight Car #6 June 2025 - August 2025
*Please note that occupants may experience longer wait times during the passenger car modernizations.  As such, access to Freight Elevator Car #5 has been made available while modernization of the passenger cars is being completed. 

SCHEDULE: May 13, 2024 – TBD 2025

ADDITIONAL INFORMATION:

  • All impacted buildings to remain open, all floors will remain accessible, limited efficiency in vertical transportation may be experienced during the project

 

6347 N. Broadway Renovations

PROJECT NAME:

6347 N. Broadway Renovations

PROJECT INFORMATION:

Renovations of a newly acquired asset at 6347 N. Broadway. Adaptive re-use to include bringing online 9 new classrooms for the University. The classrooms will include a variety of active and didactic pedagogies diversifying and modernizing our current inventory. The building will also provide new offices and an event space at the storefront level. 

SCHEDULE: May 2025 – August 2026

ADDITIONAL INFORMATION:

[exterior rendering coming]

Campion Hall Demolition

PROJECT NAME:

Campion Hall Demolition

PROJECT INFORMATION:

Site demolition clearing the way for building a better Loyola.  

SCHEDULE: May 2025 – December 2025

ADDITIONAL INFORMATION:

  • Furniture move-out and donation - May 2025
  • Interior abatement - June 2025
  • Structural demolition - 4th of July through November 2025
  • See campus plan: Campus Plan

 

 

Cudahy Library Exterior Renovations

PROJECT NAME:

Cudahy Library Exterior Renovations

PROJECT INFORMATION:

Façade renovations to include masonry renovations, lintel replacements, exterior window and door repairs. 

SCHEDULE: May 2025 – August 2025

ADDITIONAL INFORMATION:

[exterior photo coming]

 

Golf and Softball Practice Facilities and Mertz Amenity Deck Renovations

PROJECT NAME:

Golf and Softball Practice Facilities and Mertz Amenity Deck Renovations 

PROJECT INFORMATION:

Converting the decommissioned Mullady Theater into the new and permanent home for women's and men's golf. This space will also be converted to become the permanent home for women's softball. In addition, a renovated rooftop plaza will feature a pergola, synthetic turf, and seating.

SCHEDULE: May 2024 – August 2025

ADDITIONAL INFORMATION:

April 2025:

April 2025:

Renderings by RDG

Madonna della Strada Exterior Renovations

PROJECT NAME:

Madonna della Strada Exterior Renovations 

PROJECT INFORMATION:

Project Information: Renovations to include roof repairs, roof tile replacement, and limestone cleaning 

SCHEDULE: May 2025 – December 2025

ADDITIONAL INFORMATION:

 

School of Social Work Simulation Lab

PROJECT INFORMATION:

The first simulation space downtown at WTC will provide students with an opportunity to gain simulation experience while in school. A total of 10 interview rooms (1 family room, 9 interview rooms) as well as debriefing rooms will be included in the new lab and allow for both virtual and in-person simulation. 

SCHEDULE: Interior renovation complete; simulation technology and furniture will be installed over the summer of 2025 with the Sim Lab in use for the the fall 2025 semester

OTHER PROJECT INFORMATION:

  • The simulation lab will be located in Maguire Hall
  • Simulation lab buildout: SSW Simulation Lab

 

St. Louis Hall Exterior Renovations

PROJECT INFORMATION:

St. Louis Hall Parapet Repair & Window Replacement 

SCHEDULE: May 12th -  August 8th, 2025

OTHER PROJECT INFORMATION:

[exterior photo coming]